| Field Events | $50,000.00 | Prop A | Athletics |
| Maintenance Projects Contingency Funds | $55,690.00 | Prop A | School Buildings |
| School Safety and Security Contingency Funds | $77,250.00 | Prop A | Safety, School Buildings |
| Radios for Single Emergency System | $90,000.00 | Prop A | Safety |
| Intruder-resistant Glass | $172,000.00 | Prop A | Safety |
| Replacing Band Trailer | $200,000.00 | Prop A | Band, Fine Arts |
| Raptor Software for Lockdowns | $275,000.00 | Prop A | Safety |
| Build 4 Tennis Courts | $300,000.00 | Prop A | Athletics |
| Renovate Spring Sports Facility | $300,000.00 | Prop A | Athletics |
| Classroom Door Hardware | $330,000.00 | Prop A | Safety |
| Additional Card Readers | $355,000.00 | Prop A | Safety |
| Playground Equipment & Sun Shades | $500,000.00 | Prop A | School Buildings |
| Hardening of Exterior Gates/Fencing | $505,000.00 | Prop A | Safety |
| Replacement of Fire Alarm Systems | $535,000.00 | Prop A | Safety |
| Replacement of Intercom Systems | $609,000.00 | Prop A | Safety |
| Replacement of Select Exterior Doors | $623,000.00 | Prop A | Safety |
| Install Entry Vestibules | $828,750.00 | Prop A | Safety |
| Rebuild Main Parking Lot | $900,000.00 | Prop A | School Buildings |
| Interior Refresh Projects | $935,000.00 | Prop A | Academics |
| Sidewalks & Parking Lot Additions | $950,000.00 | Prop A | School Buildings |
| New Parking Lot | $1,000,000.00 | Prop A | School Buildings |
| Artificial Turf for Practice Field | $1,100,000.00 | Prop A | Athletics |
| Instrument Replacement | $1,300,000.00 | Prop A | Band, Fine Arts |
| Window Replacement for Energy Efficiency | $1,540,800.00 | Prop A | School Buildings |
| LED Lighting Projects | $1,672,000.00 | Prop A | School Buildings |
| Demolish Field House & Existing HS Main Building | $1,697,280.00 | Prop A | Academics, Athletics |
| Softball Complex Upgrades | $2,000,000.00 | Prop A | Athletics |
| Agricultural Science Facility Upgrades | $2,500,000.00 | Prop A | CTE |
| New Braunfels High School Stadium Upgrades | $2,500,000.00 | Prop B | Band, Athletics, Fine Arts |
| Renovate Library for JROTC | $2,532,000.00 | Prop A | CTE |
| Bus Replacement | $3,000,000.00 | Prop A | Band, Athletics, Fine Arts, CTE, Academics |
| Student Device, Staff Hardware, Network Hardware Refresh | $3,000,000.00 | Prop C | Band, Athletics, Fine Arts, CTE, Academics |
| Outdoor Sports Locker Room | $4,500,000.00 | Prop A | Athletics |
| Administrative & Project Management Fees | $5,000,000.00 | Prop A | School Buildings |
| Mechanical, Electrical & Plumbing Upgrades | $5,725,000.00 | Prop A | School Buildings |
| HVAC & Districtwide Automation Integration | $5,956,000.00 | Prop A | School Buildings |
| Roofing | $6,965,510.00 | Prop A | School Buildings |
| Phasing Costs | $7,448,764.00 | Prop A | School Buildings |
| Furniture, Fixtures & Equipment & Technology (6% of cost) | $12,722,912.00 | Prop A | Academics |
| Project Contingency (8% of total construction) | $14,527,604.00 | Prop A | School Buildings |
| Fees, Permits & Soft Costs (9% of total construction) | $16,311,425.00 | Prop A | School Buildings |
| Project Escalation | $24,814,015.00 | Prop A | School Buildings |
| Long Creek High School Stadium | $40,000,000.00 | Prop B | Band, Athletics, Fine Arts |
| Rebuild Academic/Field House Wing | $54,846,000.00 | Prop A | Academics, Athletics |
| Rebuild High School Athletics/Fine Arts | $81,750,000.00 | Prop A | Athletics, Fine Arts |