(November 2, 2021) New Braunfels ISD taxpayers approved two of the three propositions listed under the 2021 Bond that went before voters on November 2. These two propositions total $327.9 million in projects to address growth, aging facilities, athletic upgrades (excluding stadiums) and technology.
Under Proposition “A” totaling $321,300,000, the election drew an estimated 61 percent in favor and 39 percent against the bond proposition. A total of 3,204 voters were in favor of the bond and 2,028 against.
NBISD 2021 Bond
Under Proposition “C” totaling $6.6 million for districtwide technology, an estimated 59 percent of the voters cast a ballot in favor and 41 percent against. A total of 3,061 voters voted in favor and 2,157 against.
The total bond presented to voters was $348 million and also included a separate proposition – Proposition B – for a varsity competition stadium at the future Long Creek High School and upgrades to the existing New Braunfels High School press box. This particular proposition did not gain voter approval with an estimated 54 percent voting against.
Long Creek High School
Long Creek High School (LCHS) will be NBISD’s second comprehensive high school. It is scheduled to open in August 2024 at the campus that currently houses the Ninth Grade Center. Funding to add on and expand the campus is being provided through the 2021 Bond Program.
Project Team:
Huckabee Architects
Bartlett Cocke General Contractors
Phase 1 Project Status: In Progres
Phase 1 Projected Completion Date: Fall 2024
Scope of Work:
– 3-story academic wing
– Career and Technical Education
– Learning Spaces
– Expansion of Current Academic Spaces
– Band Hall Expansion
– Parking Lot Expansion
– Baseball and Softball Fields
– Four Tennis Courts (expands complex to 8 courts)
– Remodeled Administration Areas
Phase 2 Project Status: In Progress
Phase 2 Projected Completion Date: Fall 2025
Scope of Work:
– Addition of Auxiliary Gym & Expansion of Competition Gym
– Addition of Theatre and Black Box, Choir Room, Art Rooms, Dance Studio,
– Athletic locker rooms, training room and weight room
– Parking Lot Expansion


Construction crews will begin pouring additional sections of concrete at Long Creek High School the week of August 26, 2024. The overnight pours could start as early as 1 a.m.
A series of concrete pours will be required over the next ten (10) weeks to construct Phase 2 of LCHS. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process.

LCHS Concrete Pour Variance Notification for June 6, 2024
Starting the week of June 20, 2024, the construction crews will begin pouring sections of concrete for the next phase of the future Long Creek High School. The overnight pours could begin as early as 1 a.m. A series of concrete pours will be required to expand the school’s footprint. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process. If you have any questions, comments, or concerns, please email bond@nbisd.org.

LCHS Concrete Pour Variance Notification for April 8, 2024
Starting the week of April 15, 2024, the construction crews will begin pouring sections of concrete for the next phase of the future Long Creek High School. The overnight pours could begin as early as 1 a.m. A series of concrete pours will be required to expand the school’s footprint. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process. If you have any questions, comments, or concerns, please email bond@nbisd.org.

Variance #3: Concrete Pour Notice
Posted: Jan. 5, 2024
Starting the week of January 8, 2024, the construction crews will begin the next phase of concrete pours on the site. The concrete pours are expected to begin as early as 1 a.m. A series of concrete pours will be required to expand the school’s footprint. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process.
Construction Video Update for November 2023
The expansion of the Ninth Grade Center to become NBISD’s future second high school – Long Creek High School – is well underway. Concrete and structural work continues as an additional 3-story academic wing is built.
Concrete Pour Notice for Dec. 13
Posted: Dec. 12, 2023
On Wednesday, December 13, 2023, at approximately 1 a.m. the construction crews will pour another section of concrete at Long Creek High School School.
Concrete Pour Notice for Nov. 16
Posted: Nov. 15, 2023
On Thursday, November 16, 2023, at approximately 1 a.m. the construction crews will pour another section of concrete at Long Creek High School School.
Variance #2: Concrete Pour Notice
Posted: Oct. 19, 2023
Starting November 4, 2023, the construction crews will begin the next phase of concrete pours on the site. The concrete pours are expected to begin as early as 1 a.m. An early morning pour is necessary, considering the high temperatures we experience here in South Central Texas. As the weather gets cooler, we will be able to change our schedule to a later time.
Concrete Pour Notice for Nov. 21
Posted: Nov. 16, 2023
On Tuesday, November 21, 2023, at approximately 1 a.m. the construction crews will pour another section of concrete at Long Creek High School School.
Official design of the Long Creek High School Dragon is released
Posted: October 6, 2023
For more information, go to https://nbisd.org/nbisd-releases-dragon-logos-for-long-creek-high-school/

Concrete Pour Notice for Oct. 10
Posted: Oct. 9, 2023
On Tuesday, October 10, 2023, at approximately 4 a.m. the construction crews will pour another section of concrete at Long Creek High School. This means when you go to on Monday night, the crew will be working during the early morning hours to complete the work. An early morning pour is necessary, considering the extremely high temperatures we experience here in South Central Texas. If you have any questions, comments, or concerns, please call (830) 643-5781 or email bond@nbisd.org.
Concrete Pour Notice for Sept. 19
Posted: Sept. 18, 2023
On Tuesday, September 19, 2023, at approximately 1 a.m., the construction crews will begin pouring another section of concrete at Long Creek High School. This means when you go to sleep on Monday night, the crew will be working into the morning hours on Tuesday to complete the work. An early morning pour is necessary, considering the extremely high temperatures we experience here in South Central Texas. If you have any questions, comments, or concerns, please call (830) 643-5781 or email bond@nbisd.org.
Concrete Pour Notice for Sept. 8
Posted: Sept. 6, 2023
On Friday, September 8, 2023, at approximately 2 a.m., the construction crews will begin pouring the second section of concrete at Long Creek High School. This means when you go to sleep on Thursday night, the crew will be working into the morning hours on Friday to complete the work. An early morning pour is necessary, considering the extremely high temperatures we experience here in South Central Texas. If you have any questions, comments, or concerns, please call (830) 643-5781 or email bond@nbisd.org.
Successful Concrete pour on Aug. 30
Posted: Aug. 30, 2023
The first of many overnight concrete pours took place in the early morning hours on Aug. 30th. The concrete was poured to created the subfloor of the new academic wing addition.

2023-2024 School Year Traffic Flow Map
Posted: Aug. 4, 2023
The traffic flow map for the 2023-2024 School Year is now available. Please note that the one-way in and out flow of traffic has shifted to allow the various flows of traffic to access the front driveways. Please use caution when driving in the parking lot. The exit lanes will mix with construction traffic. All traffic will exit together using the second exit.

First Series of Concrete Pours to begin the week of Aug. 14
Posted: Aug. 14, 2023
Updated: Aug. 18, 2023
Starting the week of August 21, 2023, the construction crews will begin pouring the first section of concrete for the site. This process is expected to begin as early as 1 a.m. An early morning pour is necessary, considering the extremely high temperatures we experience here in South Central Texas.
A series of concrete pours will be required to expand the school’s footprint. We are working with our contractors to ensure no disturbances to you and your neighbors during this process. They have established procedures to eliminate any disruptions.
Summer 2023 Traffic Flow Map
Posted: May 30, 2023
The traffic flow map for the summer until early August is being shared to show that access to most of the campus is closed due to construction. This includes the closure of the athletic fields.

Construction Update – July 2023
Long Creek High School construction site work is underway
Design Development Presentation – April 2023
Posted: April 5, 2023
The Board of Trustees received an informational presentation on the design development of Long Creek High School. Which can be found here.
Construction Underway – March 28, 2023
The construction phase at LCHS has officially begun.
Groundbreaking Ceremony – March 23, 2023
A groundbreaking ceremony was held at LCHS the morning of March 23, 2023.

Traffic Pattern Update – Feb. 7, 2023
Starting Monday, February 13, 2023, the first phase of construction will begin at NGC to convert to LCHS. Therefore, the back road currently used for student drop off will be closed for the remainder of the year. Parents will follow the same traffic pattern as they do in the afternoon for student pick up (FOLLOW THE ORANGE ARROW FLOW IN THE PICTURE BELOW). Please avoid the bus loop illustrated by the GREEN arrows below.

Second school color selected
Posted: Feb. 13, 2023
The NBISD Board selected the second school color for Long Creek High School (LCHS) during their regular monthly board meeting on February 13. They selected the color of dark green to go with the previously selected color of navy blue. Navy blue and dark green will be the colors for the school’s new mascot – the Dragons – that was selected earlier this school year.

Navy blue named as school color
Posted: Jan. 9, 2023
NBISD has been working towards a decision regarding the colors of Long Creek High School (LCHS). Last month, NBISD announced the students who will attend the school voted in favor of the Dragon as the school’s mascot. The students then voted in favor of navy blue over a light blue, considered “Carolina blue.” Now that the mascot and primary color has been selected, student will vote on a secondary color next month. (The uniforms above will not be the actual LCHS uniforms. These were used to express the shade of blue.)

LCHS Mascot revealed
Posted: Dec. 12, 2022
The NBISD Board of Trustees unanimously approved the Dragon as the mascot of Long Creek High School. The decision was made during a regular monthly meeting on Dec. 12.
New Braunfels High School
Project Status: In Progress
Phase 1 Construction Start Date: May 30, 2023
Phase 1 Projected Completion Date: Fall 2025
New Braunfels High School, at its current site, was first built in 1963. Several additions and upgrades have been funded over the years to expand the school to a comprehensive high school. Funding provided under the 2021 Bond Program will only fund Phase 1 of 2 for the complete replacement of the campus. Funding for Phase 2 will be sought in a future bond referendum.
Phase 1 Scope of Work:
– A new 3-story academic wing
– New Career and Technical Education learning spaces
– Relocation of the JROTC facility, tennis courts and practice field
– New turf on softball and baseball fields
Project Team:
Huckabee Architects
Joeris General Contractors
NBHS Construction Snapshot January, 2026
NBHS Construction Snapshot April 15, 2025

NBHS Concrete Pour Notice for April 17, 2025, May 17, 2025 and June 7, 2025
The construction crews will pour another section of concrete at New Braunfels High School. The crew will work during the early morning hours to complete the work.
April 17, 2025 – Pour as early as 4:00 AM
May 17, 2025 and June 7, 2025 – Pour as early as 1:00 AM
NBHS Phase 1 Update Feb. 21, 2025

Concrete sidewalk at greenhouse has been poured.

Library wall baffle ongoing.

Portable access drive ongoing.

Interior storefronts in the kitchen are being installed.

Steel tree canopies are being erected.

All interior and exterior overhead doors have been installed.


NBHS Phase 1 Update Sep. 17, 2024
Construction at NBHS is well underway with Phase 1, which was funded by the 2021 Bond Program. This project is the first step in replacing the current campus, which was originally built in 1963. Over the years, NBHS has undergone several expansions, but this new development will reshape the school for a new era of education.
Phase 1 is anticipated to be completed in the Fall of 2025. Projects include in Phase 1 include:
- Construction of a new 3-story academic wing
- Creation of new CTE learning spaces
- Relocation of the JROTC facility, tennis courts and practice fields
- Installation of new turf on baseball and softball fields.
The current phase is part of a two-part plan to replace the NBHS campus. Funding from the 2021 Bond Program covers Phase 1, while Phase 2 was funded by the 2024 Bond Program.
Posted: March 1, 2024
NBISD, Joeris Construction, and a representative from the City of New Braunfels are hosting a meeting for the residents who live near NBHS and have questions or issues related to the construction. The meeting will be held on Wednesday, March 6th, from 6 to 7 PM in the NBHS Commons. Please park in the campus lot near Ohio and enter through the rear side of the building. The commons area is outside the main gym. If you have any questions, please email bond@nbisd.org.
Concrete Pour Notification for Jan. 19, 2024
On Friday, January 19th at approximately 3 a.m. the construction crews will pour an additional section of concrete at New Braunfels High School. The crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Construction Progress Photo from January 2024

Concrete Pour Notification
Posted: Jan. 12, 2024
On Friday, January 12th at approximately 3 a.m. the construction crews will pour an additional section of concrete at New Braunfels High School. The crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Concrete Early Pour Variance #2
Posted: Jan. 5, 2024
Starting the week of January 8, 2024, the construction crews will begin the next phase of concrete pours on the site. The concrete pours are expected to begin as early as 1 a.m. A series of concrete pours will be required to expand the school’s footprint. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process.
Additionally, you can sign up for email notices by clicking here.
We value you as a neighbor and greatly appreciate your patience while the school is constructed. If you have any questions, comments, or concerns, please contact me at (830) 643-5781 or by emailing bond@nbisd.org.
Concrete Pour Notification
Posted: Jan. 5 2024
Happy New Year! – On Friday, January 5th at approximately 3 a.m. the construction crews will pour additional sections of concrete at New Braunfels High School. The crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Concrete Pour Notification for Dec. 18 & 19, 2023
On Tuesday, December 12, 2023, at approximately 2 a.m. the construction crews will pour another section of concrete at New Braunfels High School. This means when you go to sleep tonight, the crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date. Happy Holidays!
Construction Update for Dec. 7, 2023
Concrete for the site slab is currently being poured in sections. A tower crane has been installed on the site for construction purposes and will lift heavy materials and equipment to their intendent location within the new building. The crane use will be limited to the area contained by the construction fence and will not impact student & staff safety.
Concrete Pour Notification for Dec. 12, 2023
On Tuesday, December 12, 2023, at approximately 2 a.m. the construction crews will pour another section of concrete at New Braunfels High School. This means when you go to sleep tonight, the crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Concrete Pour Notification for Dec. 1, 2023
On Friday, December 1, 2023, at approximately 4 a.m. the construction crews will pour another section of concrete at New Braunfels High School. This means when you go to sleep tonight, the crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Construction Update for Nov. 28, 2023

The turf installation at the softball and baseball fields has been completed. This project is in Phase 1’s scope of work at NBHS. The contractor for this project was Hellas.
Concrete Pour Notification for Nov. 7, 2023
On Tuesday, November 7, 2023, at approximately 1 a.m. the construction crews will begin pouring the first section of concrete at New Braunfels High School. This means when you go to sleep on Monday, the crew will be working during the early morning hours to complete the work. We will continue sending notices for the concrete pours closer to each date.
Concrete Early Pour Variance #1
Starting the week of November 6, 2023, the construction crews will begin the first phase of concrete pours on the site. The concrete pours are expected to begin as early as 1 a.m. These early morning pours are necessary for several reasons including the high temperatures we experience here in South Central Texas, traffic, supply and labor.
A series of concrete pours are required to construct the footprint of the replacement campus. We are working with our contractors to ensure there are no disturbances to you and your neighbors during this process and have established procedures to reduce disruptions.
Additionally, you can sign up for email notices by clicking here.
We value you as a neighbor and greatly appreciate your patience while the school is constructed. If you have any questions, comments, or concerns, please contact me at (830) 643-5781 or by emailing bond@nbisd.org.
NBHS Traffic Flow Map for August-September (Aug. 14, 2023)
The traffic flow for the first part of the school year has been adjusted due to construction. Once the front parking lot is complete, the routes will be updated.

Memorial plaques have been relocated, trees removed due to construction (July 27, 2023)
Due to the renovation of NBHS, a tree planted in 1969 in memory of a beloved student, Gary Simon, was removed. The dedication plaque for this tree along with all of the other precious memorials on campus were inventories earlier this year. The campus administration made contact with the families to let them know about the relocation of the plaques. All of those plaques or stones have been temporarily relocated along the west side of the library. It is our hope to give them a new home under one of the heritage oaks near the library once construction is completed. We have also identified several other items in the schools that are important keepsakes and will relocate them to the future building. This includes the class panoramic pictures, the artwork in the cases outside the gym and other student portraits that hang throughout the school. We also have plans to move the small mosaic unicorn mural near the indoor planter area to the new school and install a replica of the glass mural of unicorns that now stands in the Commons Area. All of these are important pieces of the school’s history that we fully intend to preserve.
Summer 2023 Traffic Flow Map
Posted: May 15, 2023
This traffic flow map is for May 30, 2023, until early August 2023. An updated map will be provided for the fall once it is finalized. The main project that will affect parking and traffic flow over the summer is the closure of the front parking lot that will be expanded and projected to be reopened in fall. The rear parking lot is projected to be closed during the entire duration of the new construction.

NBHS Summer Athletics Camp Drop-off/Pick-up Map
Posted: May 22, 2023
NBHS we will under construction starting May 30th. These traffic flow maps are for May 30, 2023, until early August 2023. This map is being provided to show designated drop-off and pick-up locations for summer camps. For more informaiton regarding Athletics Summer Campus visit https://nbisd.store.rankone.com/Camp/List

Lamar Elementary School (ES #11)


This school is being built to provide relief to Veramendi Elementary and future capacity issues at Lamar Elementary. It is located off of Loop 337 near Oakwood Church in the Veramendi Development.
Project Status: Completed
Projected Start Date: January 2024
Projected Completion Date: August 2025
Project Team:
Huckabee Architects
Bartlett Cocke General Constractors
Relocation of Lamar FAQ
ES#11 (New) Lamar Construction Snapshot 7-25-25
ES#11 (New) Lamar Construction Snapshot 7-17-25
ES#11 (New) Lamar Construction Snapshot 7-10-25
ES#11 (New) Lamar Construction Snapshot 7-3-25
ES#11 (New) Lamar Construction Snapshot 6-19-25
ES#11 (New) Lamar Construction Snapshot 6-12-25
ES#11 (New) Lamar Construction Snapshot 5-15-25
ES#11 (New) Lamar Construction Snapshot 5-8-25
ES#11 (New) Lamar Construction Snapshot

ES#11 (New) Lamar Construction Snapshot

ES#11 Notice of 10-Week Early Concrete Pour Variance
Starting October 8, 2024, the construction crews will begin the next phase of concrete pours on the site. The concrete pours are expected to begin as early as 1 a.m. A series of concrete pours are required to construct the footprint for the campus expansion.

ES#11 Update Sep. 17, 2024
Exciting developments are underway in NBISD as construction on Elementary #11 (site of the new Lamar Elementary School) is officially in motion! Designed to address growing enrollment needs, this school will offer relief to Veramendi Elementary and tackle future capacity concerns at the existing Lamar Elementary.
Nestled off Loop 337 near Oakwood Church in the Veramendi Development, the new campus is anticipated to open in the Fall of 2025.
The Lamar Elementary project is a key part of NBISD’s ongoing efforts to provide innovative learning environments for our students. Stay tuned for more updates as this new campus begins to take shape!
ES#11 Early Pour Variance Notice for Aug. 5, 2024
Beginning Aug. 5, 2024, the construction crews will begin pouring concrete at the future Elementary School #11 being built near Oakwood Church. The crews will work during the early morning hours to complete the work. This variance is for 10 weeks and will allow pours to begin as early as 1 a.m.

ES#11 Groundbreaking Ceremony May 9, 2024
A groundbreaking ceremony was held on May 9, 2024, for Elementary #11. View the related story at: https://nbisd.org/

ES#11 Concrete Pour Variance Notification for June 6, 2024
Starting the week of June 20, 2024, the construction crews will begin pouring sections of concrete for the future Elementary School #11. The overnight pours could begin as early as 1 a.m. A series of concrete pours will be required to expand the school’s footprint. The contractor has established procedures to reduce any disturbances to you and your neighbors during this process. If you have any questions, comments, or concerns, please email bond@nbisd.org.

Schematic Deisgn Approval (Aug. 15, 2023)
The schematic design was approved by the Board of Trustees on August 14, 2023. The next step is the Design Development Phase and approval of the General Contractor for the project.

Klein Road/Voss Farms Additions
Project Status: In Design
Project Start Date: July 2023
Projected Completion Date: Fall 2024
Project Team:
Huckabee Architects
Dawson Construction
Scope of Work:
– Classroom wing addition at Klein Road Elementary
– Classroom wing addition at Voss Farms Elementary
These two projects are being implemented to address future capacity issues at both campuses. The project includes a classroom wing at each school to provide additional classroom space.
Construction Update for July 2024
KRE final section of concrete is poured
The last section of the concrete slab has been poured, and the retaining blocks have been placed and grouted around the perimeter.
Construction Update for December 2023
Klein Road site work begins: On Nov. 27, the construction for the addition began after final permitting from the City of New Braunfels was received.

Voss Farms excavation work continues: The excavation work to install the storm sewer and lateral sewer drain is still underway.

Construction Update for November 2023
Construction work at Voss Farms began earlier this month. The current site work involves utility work and excavation related to the sewer tie-in and storm pipe installation.

Playgrounds & Shade Structures

The new playgrounds and playground shades are being installed to not only replace aging structures but also upgrade the playscapes.
Project Start Date: March 2023
Projected Completion Date: September 2023
Project Team:
Miracle – Park Place
Scope of Work:
– New Playground Structures at Klein Road, Memorial, County Line, Walnut Springs, Lone Star Early Childhood Center and Lamar
– New Playground Shades at Klein Road, Memorial, County Line, Walnut Springs, Lone Star Early Childhood Center, Lamar, Veramendi and Voss Farms
Seele Elementary Renovations

The school was built in 1950 and currently houses nearly 300 students in Kindergarten through 5th Grade. Plans are currently underway to renovate this school with funds from both the 2021 Bond and 2024 Bond.
Project Status: On Hold
Project Start Date: TBD
Projected Completion Date: TBD
Project Team:
TBD
Scope of Work:
– To be determined as priority projects are identified